A last test has revealed the safety of the Barrier Dam, the sluice facilities, and locks to be inadequate. Rijkswaterstaat is working together with the provinces of Fryslân and Noord-Holland and the municipalities of Wieringen and Wûnseradiel on exploring the future of the Barrier Dam. DHV has submitted an outlook for the future for the Barrier Dam, with the title “WaddenWerken”.

The height of the dike will not be increased, but it will be widened with tidal land, resulting in a solid barrier that expands with the sea. This technique, in which processes of natural sedimentation are accelerated with simple means, is centuries old. However, it has never before been used on such a scale as part of the safety concept.

The tidal land is 400 to 600 meters wide. There is a tidal land ridge approximately 100 meters wide between the tidal land and the Barrier Dam. This ridge is connected to the Barrier Dam by a depression. WaddenWerken is designed so that the Barrier Dam (1932) remains recognizable, heritage values are safeguarded, and ecological values are reinforced.

Clever use of the - new – sluice gates in combination with lee banks softens the effect of freshwater “shocks”. The construction of salinity gradients is also part of the vision. Extracting the required sand from Lake IJssel allows for the creation of diverse underwater scenery attractive to fish and birds.

WaddenWerken entails two bridges, functioning as access gates to Friesland and Noord-Holland, with a view on Wadden and Lake IJssel. These bridges constitute an elegant and structural solution for the currently at-grade intersection of road and shipping traffic. “Blue Energy”, which is energy from the difference between freshwater and saltwater, can be developed. A Climate Center is being developed on Kornwerderzand.



"We are always searching for alternative environment-friendly solutions." Marjan den Braber Read More

The storm surge barrier in the Neva Bay is intended to protect Saint Petersburg and its 5 million residents from floods. Construction began already in 1980, but it was not completed due to environmental issues. From 2003 to 2008, DHV and its partners worked on the completion of the storm surge barrier. We were responsible for the design, the tendering process, and support of execution. With a length of 25 km, the storm surge barrier is one of the most complex barriers in the world.

Background

The initial plans for the construction of the storm surge barrier date from 1923. The Russians began construction in 1979. That construction was suddenly stopped in 1988 due to a presumed negative impact on the environment. In 1990, an international committee concluded that the environmental impact of the storm surge barrier was acceptable and recommended that the construction be completed as soon as possible. In 2003, the client, Gosstroy, finally entered into a contract with an international consortium for the completion of the storm surge barrier. The consortium consisted of DHV, British Halcrow, Norwegian Norplan, and the Russian subcontractor Lenhydroproject.

Project

With a length of approximately 25 kilometers, the storm surge barrier is the largest and most complex barrier in the world. The barrier is outfitted with six lock complexes, a tunnel, a moveable bridge, 23 kilometers of dikes, and two passages for shipping that can be closed off. The design of one of those passages has been modeled on the Rotterdam Maeslant Barrier and is moveable. A highway has been built over the entire length of the barrier, serving as a beltway around Saint Petersburg. The total construction cost amounted to 1.2 billion dollars.

As the consortium leader, DHV was responsible for the complex hydraulic engineering barriers, the dikes, and the tunnel construction. The work concerned geotechnical surveys, determination of the preconditions concerning waves, and two- and three-dimensional mathematical and physical modeling. In addition, it concerned the design of dikes, moveable barriers, bank revetments, breakwaters, dredging and land reclamation, the harbor for maintenance work, construction of quays, L-shaped structures in high-density concrete, the tunnel under the navigable channel, and the encasing of the steel doors belonging to the largest moveable barrier.



"An expert completion of a megaproject." Ben Reeskamp Read More

In Shanghai, DSM has built a new R&D campus that also contains the headquarters of the Chinese branch of the chemical group. The complex is also one of the first LEED Gold-certified buildings in China. DHV integrates a number of green techniques to enable the multinational to meet the international norm for sustainability.

Optimal orientation of the building, renewable energy, and water recycling make the DSM complex exceptionally sustainable. It is so sustainable that it qualifies for a LEED (Leadership in Energy and Environmental Design) Gold Certificate. Insulation minimizes the energy requirements; maximum use is made of daylight and solar heat; and DHV uses as much as possible local recycled materials.  Green roofs function as water buffers and ensure a comfortable interior climate. DHV’s Total Design Management ensures that all aspects are optimally geared to one another. Exactly that integration allows you to achieve the highest environmental gains. The potable water savings are 70 percent and the energy savings 30 percent.

The opening of the complex in Shanghai’s Pudong New Area took place at the end of 2008.



"Deserving the certificate Leadership in Energy and Environmental Design." Li Hua Read More